PROJECT DESCRIPTION
Extensive infrastructure upgrades including air conditioning the entire 260,000 SF school. MEP
renovations of 30,000 SF of the school and the addition of new 60,000 SF wing. Additions include a twenty-four (24) classroom science and educational wing, featuring ten advanced technology chemistry labs, and a choral music pavilion. The cafeteria was renovated and expanded to create a 'food court' atmosphere.

MECHANICAL SYSTEMS
Added central cooling plant, 1500-tons. Updated 2-pipe system with new unit ventilators and
controls throughout the building. Replacing some older AHU's. New 100-bhp re-heat boiler.
Updating all controls to fully DDC.

ELECTRICAL SYSTEMS
New 15KV tap of existing switch gear to feed addition. Replacing fire alarm system. Replacing
clock system. Updating and expanded paging system. New 100KW emergency generator.
All new energy efficient lighting in addition and retrofitting existing lighting system with T8 lamps
and electronic ballasts.

PLUMBING SYSTEMS
Lab neutralization system for one hundred eight (108) new lab sinks. Extending existing hot and cold water, gas piping system for new classrooms/labs and public toilet rooms.
Updating some bathrooms to ADA. New connections to fully renovated and expanded kitchen. New roof drainage system in areas of renovation.
Replacing domestic booster system.

2773 Philmont Avenue • Huntingdon Valley, PA 19006 • (215) 947-4562 (ph) • (215) 947-6014 (fx) • Email E&M
Web site and all contents Copyright YourName 2005, All rights reserved. Free website templates
HOME WHAT'S NEW OUR ENGINEERSFIRM PORTFOLIO ON THE BOARDSIN CONSTRUCTIONAWARDS CONTACT US